BC Hydro has updated the power restoration estimate. It is now 11:00PM PST. Cedar technical support staff will begin recovery Friday January 7, 2022 at 8AM PST | |
BC Hydro has updated the power restoration estimate. It is now 10:00PM PST | |
BC Hydro has updated the power restoration estimate. It is now 9:00PM PST | |
BC Hydro estimates that power will be restored to the SFU datacenter at approximately 6:45PM PST |
Service | Incident status | Start Date | End Date |
---|---|---|---|
Cedar | Closed |
Power outage - Panne électrique
There is a power outage at this site. / Il y a une panne de courant sur ce site. Details North of BEAVERBROOK CRS, West of AILSA AVE, South-East of UNIVERSITY DR Outage cause Snow storm Crew status Crew assigned Est. arrival Jan 6, 11:45 a.m. Last updated Jan 6, 12:58 p.m. For updates see https://www.bchydro.com/power-outages/app/outage-map.html with the zipcode V5A 4Y4